us-sc-washingtonAfter years of negotiation and lawsuits, Snohomish County agreed to let King County build a sewage treatment plant in south Snohomish County. As part of the settlement, King County agreed to provide a substantial mitigation package for the local Snohomish County community near the plant. The cost of the mitigation was included in the capital cost of the plant. Two local utility districts that contract with King County for sewage treatment filed suit, arguing that the mitigation package was excessive, among many other claims. The trial judge largely rejected the districts’ claims. After careful consideration of the record, the Supreme Court largely affirmed.